Unjust Enrichment-Construction lien action
Unjust Enrichment-Construction lien action: If a construction lien claim is struck down because the claim does not meet the technical requirements of the Construction Lien
Unjust Enrichment-Construction lien action: If a construction lien claim is struck down because the claim does not meet the technical requirements of the Construction Lien
Construction Lien Claim – Name of lien claimant-Strict Construction: When the owner consented to the amendment of the lien claimant to the name of the corporate
Construction Lien Action- Trust Fund Claim by Supplier: In order for a trust fund claim to arise under s. 8 of the Ontario Act in
Construction Lien Act- Date of last supply of services or material: Repair or deficiency work will not extend the 45 day period under s. 31
Construction Lien Act – Date of last supply of services and materials: The attendance by a paving reinforcement subcontractor at an off-site meeting to deal
Construction Lien Act-Date of last supply of services and materials-Consultant: The supplier returned to site to install materials due to error in instructions from owner.
Construction Lien Act – Lien by related company: If the lien is filed by a related company to the owner such that it would be
Bonds – Construction lien action – Intervention by bonding company: A bonding company which has issued a Form 15.1 bond in lieu of the land