Date of last supply of services or material
Construction Lien Act- Date of last supply of services or material: Repair or deficiency work will not extend the 45 day period under s. 31
Construction Lien Act- Date of last supply of services or material: Repair or deficiency work will not extend the 45 day period under s. 31
Construction Lien Act – Date of last supply of services and materials: The attendance by a paving reinforcement subcontractor at an off-site meeting to deal
Construction Lien Act-Date of last supply of services and materials-Consultant: The supplier returned to site to install materials due to error in instructions from owner.
Construction Lien Act – Lien by related company: If the lien is filed by a related company to the owner such that it would be
Bonds – Construction lien action – Intervention by bonding company: A bonding company which has issued a Form 15.1 bond in lieu of the land
Discovery planning is not necessarily part of a lien action since s. 67(2) of the Ontario Act mandates that interlocutory proceedings are not to be
Construction Lien Action – Security for Costs In a motion by the defendant to require the plaintiff in a lien action to post security for
Leave to bring a summary judgment motion can be granted under s. 67(1) of the Ontario Act in a construction lien action; 6007325 Canada Inc.