Alberta Court Applies Principles Of Contract Interpretation And Limitations To A Client-Consultant Contract

In the recently released decision in Riddell Kurczaba Architecture Engineering Interior Design Ltd v. Governors of the University of Calgary, 2018 CarswellAlta 10, 2018 ABQB 11, the Alberta Court of Queen’s Bench applied three potential aids to the interpretation to a client-consultant contract: contra proferentem; post-contract conduct; and estoppel. The court also applied the limitation period to a claim for a percentage-based fee.

The Interpretation and Limitations Issues

After the project was finished, the architects asserted that, on a proper interpretation of the client-consultant agreement, the fee should have been paid on a percentage basis, not a fixed fee basis. The architect relied upon the principle of contractual interpretation known as contra proferentem since the client (the University) had prepared the six drafts of the agreement. The owner asserted that the fee was a fixed fee, and also said that the contract should be interpreted in light of the parties’ actual performance of the contract and that the consultant was estopped from asserting that the fee was based on a percentage of the cost of construction.

The owner also asserted that the consultant’s claim was barred by the limitation period since more than two years had expired from the time when, if the consultant was correct, the fee would have amounted to more than the consultant was paid under the contract and the consultant knew or should have known that the owner was in breach of the contract.

Contra Proferentem

The Alberta court held that there was very little, if any, place for the application of the contra proferentem rule in the present circumstances:

“Where an ambiguity arises in respect of a matter that has been specifically flagged for future negotiation between two sophisticated parties, it should be resolved through the usual principles of contractual interpretation. This includes have regard to the factual matrix and, in some limited circumstances, post-contract conduct that might assist in determining the objective of the parties. The doctrine of contra proferentem has very limited utility or application in that analysis.”

Post-contractual conduct

During the performance of the contract, the parties proceeded on the basis that the fee was a fixed fee, not a percentage fee, but that the consultant was entitled to extra payment for work done in relation to change orders. The Alberta Court held that, in interpreting the contract, it was proper to look at this post-contractual in arriving at the proper interpretation of the contract, particularly when the conduct was consistently and unambiguously in favour of one interpretation:

“…..Such post-contract conduct is not properly considered as part of the factual matrix bearing on the intention of the parties at the time the contract was entered into. It may be considered, however, in the resolution of ambiguity in the contractual language used: Shewchuk v Blackmount Capital Inc., 2016 ONCA 9123 at 41….A cautionary approach is required where evidence of such subsequent conduct is used for the purpose of divining intention. It must generally be given limited weight, but “will have greater weight if it is unequivocal in the sense of being consistent with only one of the two alternative interpretations that generated the ambiguity triggering its admissibility”: Shewchuk at para 54. In this case, the language used in each of the six Change Orders signed by the parties during the project is both consistent and unequivocal in treating the work done by RKA as being part of the basic services. The language is also consistent with being compensated through adjustments to the “Fee for Service” under Section 1 of Schedule C to the Service Agreement.” (underlining added)

Estoppel

For the same reason, the Alberta court held that, by conducting itself throughout the project on the basis that the fee was payable on a fixed basis, the consultant was now estopped from asserting the contrary:

“…..it is reasonable to infer from the evidence that, had RKA refused to approve and sign-off on the Change Orders as worded, there would have been, at minimum, a discussion and negotiation of how RKA should be compensated, having regard for the wording of Article 4.3.2 and the fee negotiation contemplated in respect of fees for “Additional Services.” By RKA acquiescing in the Change Order process as implemented, only to assert its entitlement to additional fees well after conclusion of the project, the University was deprived of that negotiation (or termination) opportunity to its detriment…… Accordingly, had I accepted the position of RKA regarding the proper interpretation of the Service Agreement, I would have nonetheless found them to be estopped from claiming damages for breach of the Service Agreement.”

The Limitation Period

The Alberta Court held that the consultant’s claim was barred by the Alberta two year limitation period. If the consultant was correct that the contract provided for a fee based on a percentage of the cost of construction, then during the course of the project it would have been apparent to the consultant that the cost of construction had much exceeded the projected cost and that the consultant was owed a much higher fee than was being paid to it. More than two years passed from that point in time before the consultant made its claim.

The consultant asserted that the fee was not truly payable until its legal entitlement to percentage-based compensation was known, which it asserted was not known until the building was complete and the construction costs were known with certainty.

The Alberta court accepted the owner’s submissions:

“The $21,000,000.00 in “Construction Cost” (including contingency) set out in Schedule C of the Service Agreement was exceeded at an early stage. By this time, which was approximately January 2009, 75% of “Total Service Fee” had already been billed. It is also clear that RKA was being paid for ongoing work, excluding the separately negotiated FFE Agreement, pursuant to a series of Change Orders purporting to contain add-ons to the basic services fee described in Section 1 of Schedule C…..Accordingly, the essential facts supporting a breach of contract under RKA’s interpretation of the Service Agreement were probably known as early as March 23, 2009. These facts were certainly known when the post-project reconciliation of amounts paid to RKA, as against amounts owing under the contract, was done in March 2010. Accordingly, if RKA is correct in its interpretation of the Service Agreement, and is not estopped from claiming a breach, it would nonetheless have been out of time pursuant to the Limitations Act.”

The Merits Of The Claim

The court reviewed what it described as the “poorly drafted” and “confusing and ambiguous language” of the contract. Thus, the RFP for the contract stated that the “fees will be based as a percentage (%) of the total construction budget” and the heading to Article 4.3 of the contract stated that the fee was a “Percentage-Based Fee”. However, article 4.3.2 stated: “For greater certainty, the Fee for Services as set out in Schedule C is a fixed fee, and there will be no adjustments to the fee in the event of changes in Construction Cost due to inflation. The fee will only be adjusted in the event and in accordance with an approved Change Order which changes the Scope of Work and results in an upward adjustment in the Construction Cost or Contract Time.” Schedule C to the contract stated: “(a) Fixed Base Fee…”

After sifting through all this inconsistent language, the Alberta court held that the contract provided for a fixed fee, not a percentage fee based upon the cost of construction. The court also held that the consultant was entitled to extra fees in relation to work done on the change orders:

“Article 4.3.2 shows that the parties intended that the fee for services be a fixed fee….. Although poorly drafted, Article 4.3.2 also shows that, on an objective basis, the parties intended that compensation for basic services in respect of changes to the scope of work being done, as opposed to “Additional Services,” are to be governed by Article 4.3 and the corresponding provisions of Schedule C…..The language used by the parties in Article 4.3.2 allows the University to exercise a measure of cost control by reviewing and approving Change Orders, and to adjust the base fee for services through the Change Order process. Section 1.3(a) of Schedule D of the Service Agreement includes, as “Additional Services,” revising or providing additional drawings, specifications, or other documents “caused by instructions inconsistent with instructions or written approvals previously given by the owners, including revisions made necessary by adjustments in the Owner’s program or Project Budget….The better view, however, is that the inclusion of services associated with a scope of work change in Article 4.3.2 was intended to bring them within the ambit of services compensable through adjustment to the fixed base fee as set out in Section 1 of Schedule C.”

Accordingly, the court dismissed the consultant’s claim for further fees based on a percentage of the cost of construction.

Discussion

It is not often that one construction law case deals with a number of contract interpretation principles and the limitation period. This decision will be a useful guide to those principles for application in similar circumstances.

The court was strongly influenced by the fact that, throughout the project, the consultant participated in the calculation and payment of the fee on a fixed fee basis, and did not suggest, until the project was well over, that the fee should have been paid on a percentage basis. Clearly there is a lesson for consultants here: be up front about the basis for the fee, and don’t try to assert a different basis after the fact.

The court’s conclusion on the limitations issue might be contentious. Under section 3(1) of the Alberta Limitation Acts, the limitation period starts to run when the claimant knew or ought to have known that: (i) injury for which the claimant seeks a remedial order had occurred, (ii) that the injury was attributable to conduct of the defendant, and that the injury, assuming liability on the part of the defendant, warrants bringing a proceeding.

Accordingly, the limitation period only commences when the cause of action arises and (not or) the claimant knows or ought to know that it has a claim. In other words, the fact that the claimant knows or ought to know that the defendant’s conduct amounts to a breach of contract, and that the claimant will have a claim, does not start the limitation period unless the time for the obligation to be performed has arrived and an accrued cause of action exists (unless the claimant treats the defendant’s conduct as an anticipatory breach of contract and terminates the contract forthwith).

If the fee in this case was payable by installments, and each instalment was itself legally due and payable during the project at the stipulated time or event, then the limitation period for each payment then arose. But if, on the proper construction of the contract, the fee was one fee only earned on the completion of the project, although payable during the project by way of part-payments, then the limitation period would only arise when the fee was fully earned. And even in the first case, the limitation period would only expire payment by payment, and would not expire for those payments payable less than two years before the action was commenced.

The Alberta court did not discuss when the cause of action for the fee payments arose. In its view, the essential question was: “when the facts giving rise to the claimed breach were known or discoverable.” It further stated: “The $21,000,000.00 in “Construction Cost” (including contingency) set out in Schedule C of the Service Agreement was exceeded at an early stage. By this time, which was approximately January 2009, 75% of “Total Service Fee” had already been billed.” It appears to have assumed that the obligation to pay had by then arisen. If that assumption is correct, then the court’s conclusion is correct. If the obligation to pay had not yet arisen, even though the clamant had submitted interim bills, then the court’s conclusion may not be correct. In addition, if any of the client’s payment obligations fell within two years of the commencement of the action, then the action may have been timely with respect to those payment obligations.

All of which is to say that the parties to a building contract that take a long time to perform should be careful about limitation periods that may arise during the contract. A building contracts is usually considered to be “entire”, “dependent” or “whole” contract, under which the obligations are not independent but dependent on one another, and not fulfilled until entirely fulfilled. However, the part payment obligations under a building contract are usually considered to be severable and presently enforceable as to each payment. This is how the Alberta court considered the payments under this consultant’s agreement. The issue may be disputable under another building or consultant’s contract.

See Heintzman and Goldsmith on Canadian Building Contracts (5th ed.), chapter 1, part 3(f), chapter 2, parts 2(3)(f), 2(4)(iii) and chapter 9, part 3(a).

Riddell Kurczaba Architecture Engineering Interior Design Ltd v. Governors of the University of Calgary, 2018 CarswellAlta 10, 2018 ABQB 11

Building Contracts – Interpretation – Estoppel – Contra proferentem – Post-contract conduct – Limitation periods

Thomas G. Heintzman O.C., Q.C., LL.D. (Hon.)                     January 29, 2018  

www.heintzmanadr.com

www.constructionlawcanada.com

 

 

 

Notice Commencing Several Arbitrations Held Not To Be Totally Invalid By B.C. Court

In South Coast British Columbia Transportation Authority v. BMT Fleet Technology Ltd.

2017 CarswellBC 2587, 2017 BCSC 1683, the British Columbia Supreme Court recently held that a single notice purporting to commence several arbitrations against several respondents was procedural invalid. However, the notice was not totally void and could be amended by the applicant to provide for several arbitrations and thereby correct the procedural irregularity.

In view of the absence in most arbitration statutes of the right to consolidate arbitral proceedings, this decision is important as it allows an apparently invalid commencement of arbitral proceedings to stand in a corrected form. Whether this decision has any application to arbitrations outside British Columbia, or to an ad hoc arbitration, are issues to be considered.

Background

South Coast British Columbia Transportation Authority (known as, and referred to in this article as, TransLink) entered into two separate contracts with a ship architect, a contract with a ship consultant and a contract with a shipyard for the design and construction of a new ferry. Each contract contained a clause requiring arbitration of any disputes under the British Columbia Arbitration Act.

On April 1, 2011, TransLink delivered a Notice to Arbitrate to the British Columbia International Commercial Arbitration Centre (“BCICAC”). The notice purported to commence one arbitration proceeding under all the contracts against each of the architect, consultant and shipyard. TransLink paid a fee of $1,680 ($1,500 plus H.S.T.), the fee to be paid for one arbitration proceeding for a claim over $50,000. The Notice identified each respondent and the respective contracts with TransLink, set forth the relevant provisions of each contract and separately identified each cause of action and remedy being sought against each party.

BCICAC opened File No. DCA-1313 and wrote to the parties notifying them of the arbitration, stating in part “We acknowledge receipt of a Notice to Arbitrate (the “Notice”) . . . on behalf of . . . TransLink . . . received at this office on April 1, 2011. This arbitration is deemed to have commenced on April 4, 2011.”

Then counsel for the shipyard telephoned BCICAC to raise concerns about the propriety of a single arbitration proceeding against multiple parties under multiple contracts. TransLink advised BCICAC that the Notice to Arbitrate “may have been irregular”. BCICAC suspended the Arbitration until they “have had the opportunity to discuss the form of the Notice further with counsel”. Various correspondence was exchanged and then in May 2011, BCICAC advised TransLink that if it decided to proceed with arbitration, separate Notices to Arbitrate would have to be filed with the BCICAC since the respondents were not bound by the same arbitration agreement.

The parties participated in an unsuccessful mediation of their differences, and in April 2016, TransLink issued and served a Notice to Appoint an Arbitrator, to which the respondents replied, amongst other things, that the issue of the propriety of the commencement of the arbitral proceeding against several respondents under several arbitration agreements would have to be addressed.  Then in February 2017, TransLink’s new counsel wrote to counsel for the ship architect and consultant acknowledging that the Notice to Appoint an Arbitrator dated April 19, 2016 is “arguably irregular”, but stated that three contracts had been effectively commenced, one involving the ship architect and the other two involving the consultant. TransLink issued a new and separate Notice to Appoint an Arbitrator under each contract. TransLink’s counsel requested that BCICAC File No. DCA-1313 be administratively restructured to reflect separate arbitrations for each of the three contracts in issue, and provided BCICAC with an additional fee of $3,150 plus GST for two additional arbitrations. TransLink did not seek to maintain an arbitration against the shipyard.

TransLink then applied to the B.C. court for a declaration that an arbitration proceeding against each of the ship architect and the consultant had been effectively commenced, and for an order that a specified individual be appointed as arbitrator for each arbitration.

British Columbia Arbitration Act and BCICAC Rules

Like most of the arbitral statutes in Canada, the B.C. Arbitration Act (section 21) empowers the court to consolidate two or more arbitrations if, among other conditions, “all parties to those agreements agree on the appointment of the arbitrator and the steps to be taken to consolidate the disputes into the one arbitration.”

Unlike most other provincial arbitral statutes, the B.C. Act (section 22) provides that unless the parties to an arbitration otherwise agree, the domestic rules of the BCICAC apply to arbitrations governed by that Act, unless those rules are inconsistent with another governing arbitral statute or the B.C. Act. .

The BCICAC rules provide for the payment of fees upon the commencement of an arbitration and state (in rule 10) that “the arbitration is deemed to have commenced when the Arbitration Notice or Joint Submission has been filed with the Centre and the commencement fee paid. The Centre shall notify the parties when an arbitration has commenced.”

Decision of the B.C. Supreme Court

The B.C. Supreme Court held that the Notice to Arbitrate contained all of the information required by the rules of the BCICAC relating to the commencement of an arbitration: the names of the parties and their addresses for delivery; a brief statement of the matter in dispute; the remedies sought; a precise estimate of the amount claimed; and the number of arbitrators proposed.

The court found that “the respondents clearly understood the nature and substance of the specific claims being made against them, the contractual provisions being relied upon, the remedy being sought, and the fact that a request for arbitration was being made in respect to those claims. Had TransLink photocopied the Notice to Arbitrate and filed the same document four times (including in respect of the claim against Victoria Shipyards), there could be no dispute that it was fully compliant.” The parties had “adopted arbitration as the means by which their disputes would be resolved and must now be content with the informalities of the arbitration process.”

The court noted that BCICAC accepted the fee that accompanied the Notice to Arbitrate, stated that the arbitration was deemed to have been commenced and had not returned the funds. The court held that “BCICAC’s deeming that the arbitration proceedings had commenced is analogous to the court registry having accepted a civil action for filing. The matter of the payment of a fee is for the BCICAC to address and administer. It is not a matter between TransLink and the respondents, and does not prejudice the respondents in any way. The payment of the incorrect fee can hardly be described as a fundamental breach of the parties’ contracts or going to the substance or “root” of the parties’ rights inter se.”

Accordingly, the court found that “TransLink’s April 1, 2011 Notice to Arbitrate, although an irregularity, was effective to commence four separate arbitration proceedings”, two against the ship architect and one each against the consultant and shipyard.

The court also held that the irregularity in the appointment of the arbitrator had been remedied by TransLink by its issuance of separate notices of appointment in February, 2017. The language of Section 17 of the B.C. Arbitration Act was mandatory and required the court to appoint an arbitrator if the arbitrator was not appointed by the parties. Accordingly, the court appointed the arbitrator nominated by TransLink for each of the arbitrations.

Discussion

This decision deals with the classic problem faced by arbitration in construction projects. There is an arbitration agreement in each of the contracts between the owner and various participants in the project (say, the contractor and the consultant). There is also an arbitration agreement in each of the contracts between the various other participants in the project (say, the subcontractors, suppliers, etc). Standard arbitral law requires that there be separate arbitrations for each of these arbitration agreements, even though that will result in much greater time, inconvenience and the expense of multiple arbitrations instead of one consolidated arbitration, and with the possibility of inconsistent decisions.

The solution to this problem is not the one first adopted by TransLink, namely, the issuance of one Notice to Arbitrate under four contracts. Ultimately, TransLink did not gain consolidation of the arbitrations. Indeed, it was fortunate to end up with a court decision that validated the commencement of the arbitrations, and divided them into separate arbitrations. So TransLink was back to where it would have been had it commenced separate arbitrations.

Although the decision in this case seems fair, an appellate court might not uphold it having regard to section 21 of the B.C. Act. That section only contemplates the consolidation of multiple arbitrations with the parties’ consent. Accordingly, it might be read, by inference, as prohibiting the commencement of multiple arbitration by one commencement document. In addition, this decision might also not apply in the case of an ad hoc arbitration conducted under an arbitration agreement which is not subject to the auspices or rules of an arbitral tribunal.

The fact that the notice was accepted by BCICAC, that BCICAC stated that an arbitral proceeding was deemed to have been commenced, and that the BCICAC rules deem the proceeding to have been commenced, were key factors in the court’s decision. In effect, the court held that the fault was that of BCICAC, if there was “fault”, in accepting the single Notice of Arbitration in respect of several arbitrations, and that if there was something ineffective about that notice, then it was BCICAC that should not have accepted it. Having accepted the notice, separate effective arbitrations against each of the respondents had been commenced. The joinder of those arbitrations was an irregularity which could be cured.

The arbitration agreement contained in most Canadian building contracts provide for ad hoc arbitration, not arbitration conducted under the auspices of an arbitral institute, such as the BCICAC, ADRIC, ICC, LCIA or ICDR. Thus, the arbitration clause in the CCDC contracts does not name an institute under which the arbitration is to be conducted. If the arbitration is not conducted under the auspices of an arbitral institution, the authority of the ad hoc arbitrator to decide that multiple arbitrations were commenced by one notice to arbitration seems more doubtful.

If an arbitration is commenced under the auspices of an arbitral institution other than BCICAC, the institution’s rules may not state that an arbitration is “deemed to have commenced” when an Notice to Arbitrate is received by the institution, and the facts may not otherwise satisfy a court that multiple valid arbitrations were commenced against multiple parties just because the institution accepted the notice of arbitration and stated that an arbitration proceeding has commenced.

The better solution for the multiple arbitration problem is to deal with it up-front in the arbitration agreement in each of the contracts between the owner and other parties, such as in main contract between the owner and the general contractor and in the contract between the owner and the consultant.

That arbitration agreement can provide that each party agrees to participate in, and agrees to a consolidation of the disputes into one arbitration before one arbitral tribunal in respect of all contracts on the project. The owner and general contractor can then ensure that this sort of wording is incorporated into subcontracts through an “incorporation by reference” clause in the general contract requiring that the provisions of that contract are to be incorporated into each subcontract, and for the contractor to ensure that that occurs. That “incorporation by reference” clause may appear in either the arbitration agreement itself, or may be applicable to all the parts of the general contract that are to be incorporated into the subcontracts.

See Heintzman and Goldsmith on Canadian Building Contracts, 5th ed., chapter 11, part 4

South Coast British Columbia Transportation Authority v. BMT Fleet Technology Ltd.

2017 CarswellBC 2587, 2017 BCSC 1683

Building contract – arbitration – commencement of arbitration – consolidation of arbitrations

Thomas G. Heintzman O.C., Q.C., LL.D. (ontHon.), FCIArb              January 18, 2018

www.heintzmanadr.com

www.constructionlawcanada.com