Case Review – A.G. Clark Holdings Ltd. v. 1352986 Alberta Ltd., 2023 ABQB 219

 

Lessons Learned

  1. An affidavit’s attention to detail, backed by thorough documentary evidence in its accompanying exhibits, provides courts with the confidence to settle lien claims summarily. Choosing not to do the same with one’s own affidavit when defending a lien claim is to live dangerously.
  2. Favourable evidence reviewed by the court may prove persuasive even if it’s not formally found to be necessary to resolve the matter – or even ruled admissible.
  3. It never hurts for your expert to have the opportunity to critique the opposing expert’s work in your expert’s own report. If it’s your expert’s work that’s been savaged by their counterpart, leaving the documentary record in that condition is a risk, to put it mildly.

Facts

The owner of a historical Edmonton building hired Clark Builders to renovate it into the Redleaf Canada Presentation Centre, which involved an envelope replacement, a new roof structure, and new cladding. In other words, the building “was basically demolished and replaced.” Major mechanical and electrical elements were added to the scope of the work during the course of construction.

In accordance with the terms of the contract, Clark Builders issued monthly invoices from August 2009 to June 2011 for its services as construction manager. The building’s owner, 1352986 Alberta Ltd. (“135 Alberta Ltd.”), paid for all amounts invoiced until October 31, 2010. However, invoices from November 2010 to June 2011 totalling $475,350.80 went unpaid – 135 Alberta Ltd. alleged delay, unnecessary expense, and poor construction quality.

Clark Builders registered a builders’ lien in March 2011 against both the fee simple estate of 135 Alberta Ltd. and the leasehold interests of three corporations who had filed a caveat against the lands in question – Clark Builders claimed that those three lessees and the owner, 135 Alberta Ltd., had collectively either requested or benefited from the services of Clark Builders.

Procedural skirmishing consumed the next nine years, eventually culminating in an application in November 2020 by Clark Builders pursuant to s. 53 of the Builders Lien Act for a judgment declaring its liens valid in the amount of the outstanding invoices.

As that application ground through the system, the Builders Lien Act became obsolete with the entering into force of the Prompt Payment and Construction Lien Act in August 2022 – the Court observed that this case is likely to be one of a decreasing number settled using the old legislation.

Law

The Court’s canvas of the applicable law began by noting that Section 49(6) of the Builders Lien Act provides that “[t]he procedure in adjudicating on the claims shall be of a summary character, so far as is possible, having regard to the amount and nature of the liens in question and the enforcement of them at the least expense.”

Regarding the affidavit obliged to be filed in support of the application, the Court observed that while it was often referred to by parties as “an affidavit proving lien”, the legislation does not suggest the lienholder must “prove” the lien, but rather must provide detailed particulars of it, which precedent suggests will require “at the very least”:

  1. A statement that the lien claimant did the work or supplied the materials;
  2. Disclosure of who requested the work and materials (which would be especially important if the owner did not make the request directly);
  3. Sufficient particulars about the work or materials to allow the owner to make a reasoned judgment about payment;
  4. Finally, if there are pleadings, the affidavit should, ideally, address the issues raised in the defence.

The Court’s reflections on the case law to date emphasized the summary, expeditious nature of builders’ lien actions, which existed “[l]ong before case management was the practice in Alberta, long before the Alberta [Rules] of Court contained a provision for summary trial,” and which implied that while Rule 7.3 of the Rules of Court does not apply, the modern principles of summary judgment certainly do, foremost that:

[t]here will be no genuine issue requiring the trial when the judge is able to reach a fair and just determination on the merits on a motion for summary judgment. This will be the case when the process (1) allows the judge to make the necessary findings of fact, (2) allows the judge to apply the law to the facts, and (3) is a proportionate, more expeditious and less expensive means to achieve a just result.

The Court further cautioned against using outdated language about summary judgment to describe the suitability of a lien claim for expeditious resolution:

Observations made in earlier decades such as “[…that a] lien claim will not be dismissed or adjudicated before a proper trial of the action except in the clearest of cases [or that this] court cannot weigh the evidence and make final determinations…” are no longer the proper approach to summary dispositions.

Analysis

The Court found that the affidavit sworn by Greg Asselin, the project manager of Clark Builders, which was not challenged via questioning, was comprehensive and sufficient to satisfy the onus of proof on Clark Builders as lienholder to establish that its liens were valid in the amount of the outstanding invoices.

In doing so, it considered and dismissed the competing affidavit evidence provided by Ming Ying, the representative of 135 Alberta Ltd., which the Court criticized for not putting its best foot forward. Specifically, the Court found that it contained insufficient evidence to challenge the Clark Builders affidavit, e.g. this unfavourable comparison between the two:

Ming Ying deposes in paragraph 6 regarding completion of the interior office space: “Significant costs to complete that work were incurred ($55,268.00) which 1352986 Alberta Ltd regards as improper since these were to be included in the original budget amount.” Notwithstanding the exact number stated, no records are provided to show what those costs were for. On the other hand, Mr. Asselin’s evidence on the updated scope of work and budget set out in his June 14, 2011 letter attached as exhibit J to his affidavit confirms that the Owner “would supply flooring, interior doors, frames and hardware, PVC windows, millwork …”.

Expert Reports

After the filing of the application, the parties also exchanged expert reports regarding the value of the work performed by Clark Builders, and the experts were questioned on their reports. The Court noted that in the context of a Builders Lien Act summary procedure, which is intended to be carried out expeditiously and at the least expense, the use of expert reports to determine the validity of the liens was unusual and their admissibility was not automatic.

Ultimately, the Court concluded that in this instance the expert reports were helpful, but not necessary, to come to a satisfactory summary conclusion on the matter: the non-expert affidavits were sufficiently dispositive for the Court to declare the existence of a debt owed by the 135 Alberta Ltd. to Clark Builders in the amount of the outstanding invoices, being $475,350.80 plus GST, plus interest as defined in the construction management contract, plus costs of the application and action.

The lessees, by virtue of their caveat registered with respect to a leasehold interest in the lands owned by 135 Alberta Ltd., were not a party to the construction management contract but found to have liability for the lien registered against their leasehold interest in the amount of the outstanding invoices plus GST and interest.

Whether the Court’s remarks reflect the complete reality of the persuasive value of the duelling expert reports is questionable. The Court’s written decision describes the conclusions of the expert reports at length, including passages in which the expert for Clark Builders, writing with the benefit of the expert report for 135 Alberta Ltd., appears to have demolished the latter on several key points, e.g. the failure of 135 Alberta Ltd.’s expert to account for the difference in the cost environment between 2009 and 2011. Although the Court may not have formally taken that into account in the course of coming to its conclusion, it nonetheless seems to have made a substantial impression, and perhaps assisted the Court in confidently concluding that the matter was fit for summary resolution.

Case Review – Homegold Resources Ltd. v. Jazz Resources Inc., 2023 BCSC 423

Lessons Learned

  1. Be clear about the difference between a “draw” and a “payment”.
  2. Be aware that audited financial statements containing mention of a debt may waive a limitation defence.
  3. Don’t assume that services for which no invoice has been provided haven’t created a debt.
  4. Make your pre-trial demands reasonable or risk losing prejudgement interest from the date of the demand.
  5. Make your lien claims reasonable to avoid a potentially hefty fine.
  6. If you intend to pursue a Builders Lien Act fine on the basis of an inflated lien claim by the plaintiff, be sure to mention that counterclaim in your pleadings.

Facts

Jazz Resources Inc. is a publicly-traded junior mining company that owned a mineral tenure in B.C.’s Teddy Glacier, south of Revelstoke, where its mine was intended to produce zinc, lead, silver, and gold.

Between 2008 and 2010, Jazz extracted a 2,000-ton bulk ore sample from the mine, but that ore remained in a pile high in the mountains: a canyon-spanning bridge on the forestry road between the mine and the nearest location where the ore could be processed was dilapidated, and Jazz lacked the funding to repair it.

In early 2015, Jazz crossed paths with Robert Klenk, a financier who offered to use up to $175,000 of his own funds to rebuild the bridge. Klenk had reservations, though: Jazz was carrying substantial insider debt. Among other obligations, Bryan Glen, the former president and chief executive officer of Jazz, had been lending Jazz money to cover its operating costs through his personal company, Glen Developments Ltd., prior to his death in 2014, as well as using Glen Developments to charge Jazz for his management services.

Johan Shearer was originally a geologist employed by Jazz before becoming part of the management team. He also provided his services to Jazz through a personal company, in his case, Homegold Resources Ltd. Shearer had purchased Glen Developments from Glen’s estate and was now Jazz’s new president and chief executive officer. He agreed to Klenk’s preconditions for a loan, including that Glen Developments assign Klenk $100,000 of the debt owed by Jazz to Glen Developments.

Shearer began to retain engineers and contractors to repair the bridge, and also turned his attention to the need to build a mill to process the ore once it had been transported across the bridge. A company by the name of Neolife shipped the necessary components to the chosen site and in summer 2015 began to assemble the mill.

Now all came crashing down. The Chinese-made motors in Neolife’s mill were not approved for use in Canada, and it soon turned out the mill itself wasn’t approved for use in Canada, either: in January 2016, the provincial Ministry of Energy and Mines issued a stop work order on all construction of the mill and its associated tailings management facility until Jazz received a permit – its previous permit to construct and operate a mill having expired at the end of 2014.

Jazz had not yet received a permit by the time Shearer resigned in March 2016. When the Ministry eventually made it known in 2018 that the permit would only issue conditional on the deposit of a $481,525 reclamation bond against the risk of the site eventually requiring remediation – funds Jazz couldn’t pull together – the plan to process the ore collapsed. Jazz abandoned its claim to the Teddy Glacier and the ore was sold in its unprocessed state to a Chinese buyer.

The matter descended into litigation, and Shearer filed a claim in his own name and on behalf of his personal company, Homegold.

Homegold’s Claim

Shearer alleged that Homegold was owed nearly $300,000 in unpaid invoices for the management services he’d provided through the company, originally plead in the form of a lien claim that was abandoned before trial.

Jazz countered that as there had been no contract between Jazz and Homegold, any recovery could only occur according to the doctrine of unjust enrichment, and since Shearer had misled Jazz as to the permit status of the mill, Jazz derived little benefit from Homegold’s work.

Jazz also argued that the claim, having been initially plead as a lien claim, could only apply to Homegold’s work associated with mineral exploration, and that the administrative work itemized in Homegold’s invoices was unrecoverable.

Unjust Enrichment

It was conceded at trial that there was no contract between Jazz and Homegold, written or otherwise, and the Court concluded that Homegold’s claim would indeed need to rely on the doctrine of unjust enrichment, which requires (i) an enrichment of the defendant, (ii) a corresponding deprivation of the plaintiff, and (iii) the absence of a juristic reason for the enrichment.

The Court found without difficulty that Shearer’s substantial, unpaid efforts on behalf of Jazz established a deprivation, but the question of whether there had been an enrichment of Jazz was more complicated.

The Court found that Shearer had deliberately withheld information from Jazz, its board, and its contractors relating to the permit issue, including a written statement to investors that misrepresented the status of the permit: the Court found that he had been the only person within Jazz before the issuance of the stop work order to know that the permit had in fact expired.

However, critically, the Court also found that “it would not be appropriate to evaluate Mr. Shearer’s contributions solely based on hindsight.” Shearer would not necessarily have known of the scale of the reclamation bond that the Ministry ultimately demanded, and his misrepresentation about the permit, whether reckless or deliberate, was consequently held not to be disqualifying: his work had advanced Jazz’s ability to obtain a permit that it was reasonably believed at the time that Jazz would have the financial resources to utilize.

“Draw” vs. “Payment”

If no established category of juristic reason justifies the enrichment, such as a contract, then a court may assess the merits of recovery by considering both the reasonable expectations of the parties and public policy implications.

The financier, Klenk, argued that an oral agreement between himself and Shearer limited Shearer’s compensation to $4,000 per month. While the Court acknowledged that such an agreement would constitute a juristic reason, the Court disbelieved Klenk’s statement of the facts: the Court found that Shearer and Klenk had agreed to a $4,000 monthly draw, which the Court found to be a word that implies a partial advance on final payment.

Quantum

In valuing Homegold’s services, the Court found that the following factors weighed against Homegold:

  1. Homegold’s service rate was appropriate for technical labour but overpayment for administrative work.
  2. Because Homegold only charged in half-day increments, many of Homegold’s time entries would have resulted in overpayment relative to value provided.
  3. The delay obtaining the permit did not render all of Shearer’s work valueless, but it did render some of his work valueless, e.g., his negotiations with buyers for byproducts of ore processing that never occurred.
  4. Shearer’s work was mostly unsupervised, the tasks he undertook were largely those he personally decided to undertake, and many of those activities had proved duplicative on cross-examination.

The Court ultimately decided that of the Homegold invoices totalling $268,128 plus expenses, Homegold was entitled to payment of $100,000 plus all invoiced expenses.

Shearer’s Claim

In addition to his claim through Homegold for compensation for services rendered, Shearer also claimed in his personal capacity for money owed to him by Jazz via his purchase of Glen Developments, to which Jazz was indebted both (i) as a matter of direct loans made to Jazz by its former president and CEO through Glen Developments, and (ii) as a matter of services rendered by the former president and CEO through Glen Developments for which a rate had been agreed but which had not been invoiced.

Jazz made several arguments in response.

First, that management fees which hadn’t been invoiced did not result in a crystallized debt. The Court disagreed, finding that no physical invoice is required in order to make contractually-agreed fees payable: the Court likened the situation to a landlord not needing to invoice a tenant monthly for rent to become due. Here, one part of the written agreement between Glen Developments and Jazz obligated Glen Developments to provide management services, another part obliged Jazz to provide monthly payment, and a third part provided termination provisions. As neither party had availed itself of the termination provisions, the Court found that all of the management fees remained payable.

Second, Jazz argued that the direct loans were made via an agreement that was, per its conditions, subject to the approval of the TSX Venture Exchange, and no such approval had ever been explicitly granted. The Court disposed of that argument by finding that a fax from the Exchange confirming that the loan agreement had been “accepted for filing” was adequate: there was no evidence that the Exchange was expected to, or intended, to pass any further judgement on the loan agreement.

Finally, Jazz argued that the Limitation Act statute-barred the majority of the debt claims. The Court acknowledged that the loan agreement caused the direct loans to become due and payable in 2015 and a two-year clock began running as of that date. However, the Court found that audited financial statements issued by Jazz confirmed the claim that the debt was owed, nullifying any limitation defence.

Effect of Audited Financial Statements

Jazz retorted that the audited financial statements were inadmissible, and couldn’t be used even if admitted to prove that the debt was owed. The Court began its analysis by observing that the Evidence Act made an explicit exception to the hearsay rule for business records, and that the financial statements in question, being necessary to provide evidence on the matter, prepared in a reliable fashion, and authenticated when they were audited (Jazz being a publicly-traded company), qualified under the statutory exception for business records.

The Court then cited John B. Pub Ltd. v. Genco Resources Ltd., 2011 BCSC 657, for a detailed analysis that had led that court to conclude that financial statements could constitute an acknowledgement for the purposes of confirming a cause of action, with the effect of extending the limitation period: the balance sheet and the notes to the financial statements acknowledged the cause of action, and the confirmation of the debt was held to have occurred on the date of issuance of the financial statements.

The Court warned, however, that the fact that the financial statements constitute an acknowledgement of a claim does not mean the Court is bound to award the amounts indicated in the financial statements, and in fact with respect to the amounts claimed by Homegold, the Court declined to award the entire amount Homegold had invoiced for.

The Court, having determined that Shearer was owed money with respect to the direct debts of Jazz to Glen Developments and the contracted management fees owed to Glen Developments, found that the amount owed was $406,558, as reflected in Jazz’s audited financial statements. However, the Court also determined that prejudgment interest only began to run as of the date of the filing of the claim, not as of the date of a pre-trial demand letter, because that pre-trial demand had been for a substantially inflated sum and had demanded interest that was not in fact owed.

Builders Lien Act

Jazz ultimately sought to reduce its liability by arguing that the original claim of lien was improperly filed. It cited s. 45 of the Builders Lien Act, which states that a person who knowingly files a claim of lien containing a false statement is liable to a fine not exceeding the amount by which the stated claim exceeds the actual claim.

Jazz argued that Shearer knew or ought to have known that the claim of lien couldn’t be maintained, especially the portion of the lien claim related to non-payment for administrative work,[1]See also Chaston Construction Corp. v. Henderson Land Holdings (Canada) Ltd., 2002 BCCA 357, in which that court held that off-site work done relating to a building that was never constructed could … Continue reading and repeated its arguments regarding the lien claim being inflated.

The Court decided that no fine should issue in this case, concluding (i) that it was not apparent on the face of the evidence that Shearer had knowingly filed a false claim, (ii) that Jazz had not raised the possibility of a fine in its pleadings, and (iii) that regarding the administrative work claimed under the lien, Shearer’s responsibilities had been complex, and neither party had taken any steps to ascertain the dividing line between work that could have been the subject of a lien, work that clearly could not be, and work that would fall somewhere between the two.

Lastly, the Court observed that the common concern in lien claims is that the party improperly inflating the value of the lien is gaining leverage by precluding the owner from either disposing of or utilizing their equity in the property. In this case, the Court found no evidence that Jazz had suffered either an actual or tactical loss.

References

References
1 See also Chaston Construction Corp. v. Henderson Land Holdings (Canada) Ltd., 2002 BCCA 357, in which that court held that off-site work done relating to a building that was never constructed could not form the basis of a claim of lien.